Closing on a used catamaran will feel like a finish line, but for us it will really be the start of a very concentrated 90-day period. We do not expect to buy a boat, load our belongings aboard, and immediately point the bows toward the Bahamas. A used cruising boat—even a good one—will almost certainly have a list of survey findings, deferred maintenance, aging equipment, owner-specific modifications, and systems that need to be understood before we trust them offshore.
Our goal for the first three months is not to make the boat perfect. It is to make it safe, reliable, serviceable, and compatible with the way we plan to live aboard. Cosmetics can wait. The systems that keep water outside the hull, keep the engines running, keep the electrical system protected, and keep us anchored securely cannot.
The Refit Starts Before Closing
The survey and sea trial should already be building the refit list before the purchase is complete. We would separate findings into four categories: immediate safety issues, reliability problems, near-term maintenance, and optional upgrades. That prevents a long wish list from hiding the few items that genuinely need to happen before departure.
- Safety: through-hulls, steering, rigging defects, fire protection, bilge systems, propane problems, electrical hazards.
- Reliability: engine cooling systems, charging, pumps, refrigeration, windlass, plumbing leaks, batteries.
- Maintenance: fluids, filters, belts, impellers, bottom service, zincs, hose replacement, sail service.
- Upgrades: lithium, solar, watermaker, networking, Starlink, storage changes, electronics.

Days 1–14: Baseline the Entire Boat
The first two weeks would be about learning the boat and establishing a known maintenance baseline. Even if the previous owner kept records, we want our own starting point. We would photograph systems, label valves and breakers, record model and serial numbers, inventory spare parts, and build a maintenance spreadsheet.
Mechanical baseline
Unless recent work is very well documented, we would change engine oil and filters, inspect fuel filters, service raw-water strainers, check impellers, inspect belts, examine engine mounts, inspect exhaust components, and look carefully for coolant, oil, seawater, or fuel leaks. Saildrive or transmission oil, propellers, anodes, and shaft seals would also be checked depending on the boat.
Plumbing baseline
Every through-hull and seacock should be located and operated. We want to know which pumps feed which fixtures, how tanks are selected, where strainers are located, and what happens if a pump fails. Freshwater, bilge, head, shower sump, and waste systems all need to be mapped.
Electrical baseline
We would trace the major DC and AC circuits, inspect battery cabling, check shore-power connections, identify chargers and inverter equipment, and look for undocumented owner modifications. Before adding lithium or solar, we need to understand the existing system well enough to know what stays and what gets replaced.
Days 15–30: Fix Water, Fire, Steering, and Ground Tackle First
This is where the refit becomes less glamorous and more important. We would rather postpone a new chartplotter than postpone a questionable through-hull. The first month is about eliminating the failures that can escalate quickly.
- Service or replace suspect seacocks and hoses.
- Verify automatic and manual bilge-pump operation.
- Inspect steering cables, linkages, rudder bearings, emergency steering, and autopilot drive.
- Replace expired fire extinguishers and inspect propane shutoff and detection systems.
- Confirm anchor, chain, windlass, bridle/snubber, and backup anchor are suitable and functional.
- Correct dangerous or overheated electrical connections before increasing system loads.

Days 31–60: Build the Liveaboard Infrastructure
Once the boat is fundamentally sound, we can focus on the systems that support the cruising lifestyle we actually want. This is where electrical capacity, water independence, internet, refrigeration, ventilation, and storage move to the front of the list.
Our electrical plan may eventually center on a large lithium bank, substantial solar, a capable inverter/charger, and DC-to-DC conversion for legacy 12-volt loads. But we would not install any of that until the load analysis, cable sizing, fusing, busbars, alternator charging, monitoring, and service access all make sense as one system. Our earlier article on solar and lithium power explains the direction we are considering.
The same approach applies to the watermaker. We want the final choice to match actual tankage, electrical capability, and our real water use—not a guessed production number. Internet hardware, onboard Wi-Fi, and backup connectivity would also be installed during this phase because they affect where and how we can work.
Days 61–75: Make the Boat Easy to Maintain
A refit is successful when the boat is easier to understand after the work than before it. This phase would focus on labels, documentation, spares, access, and reducing unnecessary complexity.
- Label major valves, breakers, battery disconnects, network equipment, and filters.
- Create a digital folder with manuals and wiring diagrams.
- Build engine, watermaker, electrical, rigging, and safety maintenance checklists.
- Organize spare parts near the systems they support.
- Photograph hidden wiring and plumbing before closing access panels.
- Standardize common fasteners, hose sizes, fuses, and consumables where practical.
Days 76–90: Test the Boat Like We Are Already Cruising
The last two weeks should not be spent installing new equipment right up until departure. We want time to live on the boat, anchor out, run systems normally, cook aboard, work online, use the dinghy, make water, charge batteries, shower, run refrigeration, and discover what fails before the nearest chandlery is several islands away.

What Can Wait
Upholstery, decorative lighting, perfect cabinetry, matching hardware, cosmetic gelcoat, and other comfort projects may be worth doing, but they are easy to let into the critical path. We would rather leave with a few ugly cabinet doors and complete confidence in the bilge pumps than the other way around.
The Goal at Day 90
At the end of the first 90 days, the boat does not need to be finished. It needs to be understood. We want to know how it behaves at anchor, what it consumes electrically, how quickly it makes and uses water, what routine maintenance looks like, which spares we need, and which projects can safely wait until the next yard period.
That approach also keeps the boat purchase in perspective. The right used catamaran is not the one with zero projects. It is the one with projects we can understand, prioritize, afford, and complete without turning the dream into a permanent refit.